Greenfield D&I Facility for A Long-Time Customer

From Coil to Filled Can — The First in North America

Location: Glendale, Arizona USA

Completed: 2023

A view from the floor of a factory filled with workers wearing safety vests and hardhats while working on various machines.
A side view of a can making machine on a factory floor.
A view of a large factory floor showing various machines with catwalks above them.
A view of several tanks set up outside of a factory.
A view of a factory floor showing long assembly line machines.
A view under the hood of a can making assembly line with thousands of cans.
A long, empty assembly line on a factory floor.
A view of a factory floor showing rows of can making machines.

What We Completed

Project Summary

Roeslein teamed up with a long-time customer to engineer, design, procure and construct a state-of-the-art greenfield D&I plant in Glendale, Arizona. This facility boasts seven fully automated can making lines and has the impressive capability to run six different lines directly to the filling facility — an unprecedented achievement as the first plant in North America to do so.

Download Cut Sheet

What We Achieved

Successful Outcomes

Throughout the four-year duration of this project, seven of the eight lines’ “first pallet” scheduled completion dates were hit on time with the first line coming in weeks early and the one missed line due to long lead equipment not being available for installation.

The most significant success and what we are most proud about is the overall safety of the project. Throughout the duration of the project, including the TTW project inside our client’s filling line, Roeslein and their contractors had zero lost time incidents.

A view of a factory floor showing long assembly line machines.
A view under the hood of a can making assembly line with thousands of cans.

What We Did Differently

Innovative Methods & Solutions

One innovative solution during this project was the use of scanning and 3D modeling during the design phases. This allowed us to identify potential issues early in the process and streamline coordination between the engineering, construction and client teams.

Additionally, the use of Roeslein’s patented prefabricated modular components, specifically on one of Roeslein’s first fully outdoor Bulk Systems, reduced on-site construction time and resulted in seamless design changes in the field.

What We Faced

Main Challenges

A major challenge was managing the logistical and engineering complexities during the global supply chain challenges faced around the COVID era. Our aggressive schedule of starting one line and moving to the next lines while juggling parts caused audibles from one line to the next. One example of this was securing temporary gear motors to start one line and then replacing those motors during production when the permanent motors arrived.

A view of a factory floor showing rows of can making machines.
A side view of a can making machine on a factory floor.

What We Learned

Lessons & Discoveries

We learned throughout all phases of the project, from innovating the engineering to maintaining clear, frequent communication between engineers, constructors, and client. One standout lesson from an uncommon circumstance was to collaborate earlier with the building GC to prevent on-site clashes between building and process equipment.

What We Heard

Customer Feedback

The client expressed gratitude and high satisfaction with our commitment to safety and schedule. Our client’s record-setting start-up of these lines shows the high degree of quality that was achieved during the installation. Lastly and most importantly, our partnership with this customer and their trust of us to continue to be their integrator is the highest level of feedback we could receive.

A view from the floor of a factory filled with workers wearing safety vests and hardhats while working on various machines.

The MORE of the Story

How We Went Beyond the Ask

Both project and construction team members pulled out all the stops to hit our agreed-upon installation dates, including working Sundays, driving to other states for needed parts and using Roeslein’s deeply rooted engineering and construction management teams to steer on-site issues in the right direction.

Experienced can makers and motivated project team members streamlined their processes from drawing to the site. Our on-site team pushed themselves to safely and effectively hit green tag dates with minimal rework and overall customer satisfaction.